Treasury minutes on the third to the thirteenth reports from the Committee of Public Accounts session 2010-11

Treasury minutes on the third to the thirteenth reports from the Committee of Public Accounts session 2010-11

Author: Great Britain. Treasury

Publisher: The Stationery Office

Published: 2011-02-16

Total Pages: 72

ISBN-13: 9780101801423

DOWNLOAD EBOOK

The reports published as HC 470 (ISBN 9780215555106); HC 440 (9780215555144); HC 471 (9780215555205); HC 439 (9780215555243); HC 538 (9780215555434); HC 424 (9780215555496); HC 553 (9780215555502); HC 503 (9780215555571); HC 573 (9780215555595); HC 610 (9780215555656); HC 594 (9780215555717), session 2010-11


The right of access to open countryside

The right of access to open countryside

Author: Great Britain: Parliament: House of Commons: Committee of Public Accounts

Publisher: The Stationery Office

Published: 2007-06-21

Total Pages: 52

ISBN-13: 0215034570

DOWNLOAD EBOOK

The Countryside Rights of Way Act 2000 introduced a public right to walk across designated mountain, moor, heath, downs and registered common land in England. DEFRA tasked the Countryside Agency with opening-up the new access by the end of 2005, and the target was met with two months to spare. However the implementation of the right to roam cost the Countryside Agency £24.6 million more than anticipated, with knock-on impacts on other programmes. This report looks at the implementation of open access and the effect of the policy under the headings: encouraging the public to use the right to roam across the countryside; protecting the environment of access land and the rights of landowners; improving planning and project management. However the success of legislation is as yet unknown because there is no information on the extent to which the public are making use of their new right. In October 2006 the responsibility for open access passed from the Countryside Agency to Natural England.


H.M. Treasury

H.M. Treasury

Author: Great Britain: Parliament: House of Commons: Committee of Public Accounts

Publisher: The Stationery Office

Published: 2007-11-27

Total Pages: 44

ISBN-13: 9780215037350

DOWNLOAD EBOOK

Under the Private Finance Initiative (PFI) there are now 800 contracts with private sector suppliers for services worth in total £155 billion up to 2032. To achieve value for money, all stages of a project have to be managed effectively, including in the tendering process. The Committee, in a 2003 report highlighted a number of issues regarding the PFI tendering process (HCP 764, session 2002-03, ISBN 9780215011244). This report re-examines the tendering and benchmarking in PFI, finding that the Treasury had done little to apply what it had learned from the large number of PFI deals signed; that there has been no improvement in tendering times and significant risks to value for money continue to be taken when public authorities make late changes to deals. The Committee has set out 7 conclusions and recommendations, including: that since 2004, the proportion of deals attracting only two bidders has more than doubled with the risk of no competition; one third of public sector teams made changes to PFI projects after they had selected a single, preferred bidder; benchmarking and market testing have increased prices by up to 14%; public authorities have found it difficult to find appropriate data to benchmark PFI service costs; there is evidence that public authorities, faced with price increases have had to cut back services in hospitals, including portering, to keep contracts affordable; that there is a continuing lack of PFI experience and skills within public procurement teams.


Department of Health

Department of Health

Author: Great Britain: Parliament: House of Commons: Committee of Public Accounts

Publisher: The Stationery Office

Published: 2007-06-07

Total Pages: 48

ISBN-13: 0215034309

DOWNLOAD EBOOK

Properly managed, the use of temporary nurses can play an important role in helping hospital achieve flexibility. However their high use can have a detrimental impact on patient care and satisfaction. In 2001 the Department of Health anticipated that a growth in the NHS workforce would lead to a decline in the use of temporary staff but in spite of this intention temporary nurses still account for the same percentage of the nursing budget (around 9%). On the basis of a report by the Comptroller and Auditor General, the Committee has investigated the extent of the use of temporary nurses; whether the process is properly planned and managed; and whether there are safety and quality implications. One of the conclusions is that there has a lack of planning and it is only as a result of the problem with deficits that the NHS has taken a more co-ordinated approach


HM Revenue and Customs

HM Revenue and Customs

Author: Great Britain: Parliament: House of Commons: Committee of Public Accounts

Publisher: The Stationery Office

Published: 2007-06-12

Total Pages: 52

ISBN-13: 0215034376

DOWNLOAD EBOOK

In January 2004, the Inland Revenue entered into a contract with Capgemini to provide IT services to support the Department's business. The contract, known as ASPIRE (Acquiring Strategic Partners for the Inland Revenue), replaced two previous contracts with EDS and Accenture and, following the merger of the Inland Revenue and HM Customs & Excise in 2005, the latter's IT services contract with Fujitsu was incorporated within ASPIRE in April 2006. This change from one supplier to another was the first of this scale in the public sector, and the contract provides wider lessons for the public sector in re-competing major contracts, particularly relating to the payment of transition costs. The cost of the contract has risen from £2.83 billion to £8.5 billion over the 10 year term. Following on from a NAO report on this topic (HCP 938, session 2005-06; ISBN 9780102939170) published in July 2006, the Committee's report examines the procurement process, the transition to a new supplier and the performance of the ASPIRE contract to date. Findings include: i) before concluding the deal, the Department should have evaluated bids against a range of demands for IT services and analysed the effect of different scenarios on suppliers' prices and profit margins; ii) it should have evaluated the performance of consultants and the lessons to be learned from their use, not only for their own benefit but for that of other departments; iii) by contributing to bid costs and paying transition costs to secure competition for the contract, the Department incurred a premium of £51.9 million; iv) it should set more challenging performance targets to impose sufficient discipline on suppliers; and v) the Government should not be placed in the invidious position of having to commission further work from a contractor in order to recover compensation for underperformance.


The modernisation of the West Coast Main Line

The modernisation of the West Coast Main Line

Author: Great Britain: Parliament: House of Commons: Committee of Public Accounts

Publisher: The Stationery Office

Published: 2007-06-14

Total Pages: 60

ISBN-13: 0215034481

DOWNLOAD EBOOK

When Railtrack first planned the upgrade of the West Coast Mainline it was to have been completed in two phases in 2002 and 2005, used untried signalling technology and cost £2.6 billion. In the event the signalling was not installed, progress was much slower than anticipated and Railtrack collapsed. Network rail took over the project and put in place a more robust strategy to deliver the upgrade in three stages between 2004 and 2008. The first two stages have already been delivered on schedule. However the total modernisation cost is likely to be around £8.6 billion and the line will still be prone to overcrowding at peak times and is thus likely to need further investment. This report looks at the project on the basis of a report by the Comptroller and Auditor General.


The Impact of the Office of Government Commerce's Initiatives on the Delivery of Major IT-enabled Projects

The Impact of the Office of Government Commerce's Initiatives on the Delivery of Major IT-enabled Projects

Author: Great Britain: Parliament: House of Commons: Committee of Public Accounts

Publisher: The Stationery Office

Published: 2005-07-05

Total Pages: 48

ISBN-13: 9780215025098

DOWNLOAD EBOOK

Central civil government annually spends £2.3 billion on information technology, some 16% of its total procurement budget. This report examines the progress the Office of Government Commerce (OGC) has made in improving departments' capacity to deliver successful IT projects and programmes. In particular it looks at the application of the Gateway Review Process, where there is an independent review of projects at critical points; the use of OGC initiatives by departments; and engagement with suppliers.


Reducing Crime

Reducing Crime

Author: Great Britain: Parliament: House of Commons: Committee of Public Accounts

Publisher: The Stationery Office

Published: 2005-06-21

Total Pages: 40

ISBN-13: 9780215025074

DOWNLOAD EBOOK

The Home Office aims to reduce crime by supporting Police Basic Command Disorder Units, as well as 354 Crime and Disorder Reduction Partnerships in England and 22 Community Safety Partnerships in Wales. On the basis of evidence from the Home Office, this report examines the effectiveness and administration of these schemes. It finds that the initiatives have contributed to reductions in crime but, because they have not been systematically evaluated, it is not clear how much of a difference they have made. It also concludes that the Partnerships have too great an administrative burden and that the number of Partnerships should be reduced and their funding stream should be simplified.


Child Support Agency

Child Support Agency

Author: Great Britain: Parliament: House of Commons: Committee of Public Accounts

Publisher: The Stationery Office

Published: 2007-07-05

Total Pages: 52

ISBN-13: 0215034872

DOWNLOAD EBOOK

Since it was established in 1993, the Child Support Agency has consistently underperformed, plagued by enormous backlogs of unprocessed cases and uncollected maintenance. Where it works well, the Agency has secured regular contributions from non-resident parents and helped lift an estimated 100,000 children out of poverty. It has to administer complex assessment, collection and enforcement processes and deal with complicated emotional, financial and legal issues to bring about a degree of financial stability for children and parents. Following on from a NAO report (HCP 1174, session 2005-06; ISBN 9780102938692) published in June 2006, the Committee's report examines the implementation of child support reforms, focusing on why the problems in implementing the reforms arose, the impact on the quality of service, the remedial action taken by the Child Support Agency and the lessons learnt. The report finds that implementing the reforms has cost the taxpayer £539 million since 2000, with plans for a further £320 million to improve service levels over the next three years; but the money has failed to deliver improvements in efficiency and quality of service. The Agency still performs less effectively than its counterparts in Australia and New Zealand, with higher average costs per case and lower rates of compliance. The Government published its White Paper (Cm. 6979, ISBN 9780101697927) in December 2006, drawing on the recommendations made by Sir David Henshaw in his report "Recovering child support: routes to responsibility" (Cm. 6984, ISBN 9780101689427). Amongst the reforms announced, the Government will replace the Child Support Agency (CSA) with a new organisation, the Child Maintenance and Enforcement Commission (C-MEC) by 2008.